BHPB Iron Ore - Ore Body 25 (Eastern Ridge)

        

Scope of work for July 2013

  • Complete replacement of primary crusher
  • Complete replacement of SC01
  • Complete replacement of SC03
  • Replacement of top section of CV03

This shutdown was planned by BHP, totalling a 17 day outage, GRS were engaged to investigate the possibility of reducing down time.

GRS scoped and presented alternative methodologies to execute these works and to reduce the plant downtime to 8 days.

This was achieved by the innovative process GRS brings to all shutdowns and projects.